PMP Practice Questions
Click on a question to reveal the correct answer and explanation.
A project manager is managing a project where stakeholders frequently request scope changes.
What should the project manager do first?
- A. Reject the change
- B. Escalate to the sponsor
- C. Follow the change control process
- D. Update the schedule
Correct Answer: C — Follow the change control process
The project manager should evaluate the change request through the formal
change control process before accepting or rejecting it.
This ensures proper impact analysis on scope, schedule, and cost.
A team member reports a risk that could delay the project.
What should the project manager do next?
- A. Ignore the risk
- B. Add it to the risk register
- C. Escalate immediately
- D. Change the schedule
Correct Answer: B — Add it to the risk register
All identified risks should be recorded in the risk register
and assessed for probability and impact before mitigation actions are taken.